When The Lighthauz will be completed
Sales material says 2030. The advertising particulars in The Lighthauz e-brochure are more precise: an expected completion date of September 2030.
Key dates on record
| Item | Date |
|---|---|
| Expected completion (permit particulars) | September 2030 |
| Launch | November 2025 |
| Advertising & sales permit valid | 22 Oct 2025 – 21 Oct 2028 |
| Developer's licence valid | 4 Jul 2025 – 3 Jul 2030 |
| Approving authority | Majlis Bandaraya Pulau Pinang (MBPP) |
| Tenure | Freehold |
The developer of record is EXSIM Waterfront Sdn Bhd. The particulars describe 671 serviced apartment units in a 57-storey building; other materials we have seen say 56 storeys, so treat the storey count as approximate until the SPA.
Construction progress
EXSIM's site-progress page for The Lighthauz begins in Q2 2026, with a crawler crane on a cleared, level site. In the Q4 2026 photos several bored-piling rigs are working, with steel casings and reinforcement cages stacked beside them. Nothing has risen above ground yet.
Piling for a tower of this height on the waterfront takes time, and the whole structure is still ahead. With about four years to the expected date, that is normal for a launch from late 2025.
What the timeline means if you buy now
- You are buying almost four years ahead of keys. Early billings are small, so interest during construction is light for the first couple of years.
- The LRT Mutiara Line is also under construction; whether its waterfront station opens before or after 2030 will shape the location more than anything on this site.
- Get the delivery period and late-delivery compensation from the SPA, not the brochure.
Sent on WhatsApp
What we send on WhatsApp
Prices change by floor and units sell every week, so we send the current list instead of posting one that goes stale.
- Latest site progressRecent photos and the current construction stage
- Payment schedule & what's includedProgress billing stages and what the price covers
- Units still availableWhat's open on the floor and facing you want
Replies from a real estate negotiator (REN) with IQI Realty Sdn Bhd
The Lighthauz completion FAQ
What stage is The Lighthauz at?
Piling. EXSIM's Q4 2026 photos show bored-piling rigs at work and nothing above ground yet.
What completion date is in The Lighthauz permit particulars?
September 2030.
When did The Lighthauz launch?
In November 2025.
Keep reading
Sources & updates
Indicative prices and sizes from the developer's sales materials, checked on the date shown. The developer's final price list and SPA prevail.
- Advertising particulars (permit, licence, expected completion, tenure): The Lighthauz e-brochure
- Construction stage: our reading of EXSIM's site-progress photos, Q4 2026 update