When The Queenswoodz will be completed
EXSIM's progress-claim timeline for The Queenswoodz estimates vacant possession in Q3 2029. Its September 2026 sales summary sets completion at 52 months after the advertising permit, and the particulars in the current e-brochure, under a permit issued in March 2026, give July 2030. Q3 2029 is the developer's working estimate; July 2030 is the date the permit is based on, so plan around the later one.
Key dates on record
| Item | Date |
|---|---|
| EXSIM's estimate for vacant possession | Q3 2029 |
| Completion period in EXSIM's sales summary | 52 months after the permit |
| Expected completion (permit particulars) | July 2030 |
| Advertising & sales permit valid | 18 Mar 2026 – 17 Mar 2029 |
| Developer's licence valid | 19 Apr 2024 – 18 Apr 2029 |
| Approving authority | DBKL |
| Lease expires | 4 Mar 2123 (about 93 years left at completion) |
The particulars list two blocks: Block A with 494 units over 43 storeys and Block B with 510 units over 44 storeys, by EXSIM Jalil Link Sdn Bhd, the same company behind The Kingswoodz.
Construction progress
EXSIM's site-progress page for The Queenswoodz starts in Q2 2026, when piling rigs were working across the site. The Q4 2026 photo shows the foundation stage: pile caps and basement works, with the first lift cores starting to rise and two tower cranes up. The Kingswoodz towers, close to full height, stand right beside it.
That leaves the whole superstructure, two towers of more than 40 storeys, plus finishing, to be built in the remaining time. Nothing in the photos suggests a problem; it is simply early.
What the timeline means if you buy now
- You are buying about three years ahead of EXSIM's estimate and close to four ahead of the permit date. Early progress billings are small, so interest during construction stays low for the first year or two.
- Rent is unlikely to start before late 2029, and could slip into 2030. If you are counting on rental income to cover the instalments, budget for that wait.
- Watching The Kingswoodz next door is a fair guide to how quickly the same developer builds on the same street.
Sent on WhatsApp
What we send on WhatsApp
Prices change by floor and units sell every week, so we send the current list instead of posting one that goes stale.
- Latest site progressRecent photos and the current construction stage
- Payment schedule & what's includedProgress billing stages and what the price covers
- Units still availableWhat's open on the floor and facing you want
Replies from a real estate negotiator (REN) with IQI Realty Sdn Bhd
The Queenswoodz completion FAQ
Why are there two completion dates for The Queenswoodz?
Q3 2029 is EXSIM's own estimate for vacant possession, from its progress-claim timeline. July 2030 is the expected completion date printed in the advertising permit particulars. Plan around the later date.
What stage is The Queenswoodz at now?
Foundations. EXSIM's Q4 2026 photo shows pile caps, basement works and the first lift cores.
How many years are left on The Queenswoodz lease?
The lease expires on 4 March 2123, about 93 years after the July 2030 expected completion.
Keep reading
Sources & updates
Indicative prices and sizes from the developer's sales materials, checked on the date shown. The developer's final price list and SPA prevail.
- Advertising particulars (permit, licence, expected completion, tenure): The Queenswoodz e-brochure
- Vacant possession estimate and completion period: EXSIM's progress-claim timeline (April 2026) and sales summary (September 2026), issued to appointed agents
- Construction stage: our reading of EXSIM's site-progress photos, Q4 2026 update